Construction of improvements shall normally be complete prior to approving the final plat. However, the City may approve the final plat with certain incomplete improvements if:

A. Said improvements are more practically done later, such as the final lift of asphalt surfaces which might otherwise be marred by heavy equipment, or recreational equipment which might be vandalized if installed before the subdivision is populated, or street trees and other landscape and mitigation plantings which are better installed in a different season;

B. The applicant deposits a performance bond or cash surety, with the City as beneficiary, in an amount not less than one hundred fifty (150) percent of the City Engineer’s cost estimate for the remaining improvements; and

C. Said bond or surety specifies a period within which to complete the improvements, which period shall not exceed two (2) years from the date of final plat approval. (Ord. 2353, 2018)