To be considered valid, every permit shall have all applicable fees paid at the time of issuance and work authorized by the permit shall commence within one hundred eighty (180) days of issuance, and a minimum of one (1) inspection shall be requested and approved by the City during each one hundred eighty (180) day period to show continued progress. The work authorized by the permit shall continue to progress to completion without any work suspended or abandoned for a period of one hundred eighty (180) days. Permits for which no inspections have been requested and approved by the City within the one hundred eighty (180) day period shall be considered invalid, null, and void. (Ord. 2414, 2021)